Location
Bass Highway – Westbury Road Off-Ramp – Prospect
What We Did
Ramp re-alignment including roadworks, stormwater, street lighting
Client
Department of State Growth
Contract Value
$1.4 Million
Date
October 21 – February 22
Details
Description
The project involved the construction of a new off-ramp from the Bass Highway eastbound to the Westbury Road Interchange and closing of the existing substandard off-ramp.
The project involved the construction of:-
- Clearing and grubbing;
- Excavation and placement of embankment including importation of fill due to shortfall;
- Surface, underground and subsoil drainage;
- Stormwater structures works
- Supply and installation of streetlighting works
- Cutting of existing pavement;
- Supply and placement of pavement base and subbase material;
- Supply and placement of bitumen surfacing;
- Installation of traffic facilities, pavement marking and signs;
- Environmental management;
- Traffic management;
- Landscaping;
- New boundary fencing including security fencing
- Sundry minor works.
Special features of project:
- To be updated M.Khan
Contract Details
Form of Contract: AS2124 (BOQ)
Award Value: $0.9M (exc. GST)
Start Date: 23rd October 2021
Original Contract Period: 20 Weeks after acceptance of tender
Actual Completion Date: 28th February 2022
Liquidated Damages: Nil
Contractor Resources
Simon Heazlewood (Project Director)
Muhammed Khan (Project Manager)
Patrick Murphy (Project Supervisor)
Principal Subcontractors
Fulton Hogan (Bituminous Surfacing)
Statewide Linemarking (Linemarking)
PJ Concrete and Kerbing (Kerbing)
Reveg Tasmania (Landscaping)
Frontline Electrical (Electrical and conduit works)
Geotas (Safety Barrier)
Principal Suppliers
Boral Quarries (Quarry Product)
Hudson Civil Products (Stormwater Pipe/Structures)
Geotas (Geofabrics and subsoil drains)