Overview

Location

Maypole Creek – Newtown

What We Did

Stormwater Upgrade

Client

Hobart City Council

Contract Value

$0.95 Million

Date

July 2018 – October 2018

Details

Description

Following the devastating floods of May 2018 within Hobart and a future development proposal for a Dan Murphy’s in Newtown, Hobart City Council needed to upgrade their eroding stormwater network prior to the construction of the new development. Access to this site would be near impossible in the future due to the potential business disruption costs, hence council needed a fast and effective solution in replacing the aging stormwater network given the heritage listed building adjacent to the works, existing services and variable ground conditions.

The project involved the construction of:-
  • Stakeholder engagement.
  • Stormwater bypass system.
  • Sewer main relocation works.
  • Design and construct Soldier pile retention system.
  • Excavation adjacent to heritage building.
  • Removal of existing stormwater drainage
  • Installation of Uni-culvert stormwater units.
  • Supply and construction large stormwater direction pits.
  • Backfill of Uni-culvert stormwater units.
  • Environmental management.
  • Traffic management.
Special features of project:
  • The installation of the innovative Uni-culverts posed technical complexities owed to this product being the first of its kind used within Tasmania in a horizontal application and at such a long length. Both DCS and Hudson Civil were unfamiliar with the use of this new system and together, the project team carefully planned, designed and developed various methods to lift and install these large precast products within the tight construction tolerances for line and level.

  • The site location provided additional challenges throughout the process of the construction works. This site was originally a creek, which had been filled during a previous development. This natural watercourse provided a technical complexity in providing a safe and reliable stormwater bypass system to maintain a highly workable bedding for the Uni-culvert excavation and placement. The bypass system needed to fit within the needs of the local community and environment, hence a diesel generator pumping system could not be utilised. The DCS management team together with Netco Pumps developed a three-phase, single staged suction pump with remote access to provide low to medium flow stormwater bypass pumping arrangement.

  • Another site complexity came from the temporary engineering works required to support the existing heritage building and retaining walls, whilst excavating further below the building foundation levels. The deepest excavation was 4.5m below the existing surface level of the adjacent building. Whilst a design was nominated, the DCS team identified that this system was not constructible, nor could it provide the lateral restraint required to support the deep excavation. With the assistance of Scherzic Ground Investigations, DCS developed and installed a soldier pile shoring system strong enough to support the building and protect the DCS site personnel during the excavation and placement of the Uni-culvert system.

Contract Details

Form of Contract: AS2124 (Lump Sum)
Award Value: $0.95Million (exc. GST)
Start Date: 1 July 2018
Original Contract Period: 16 weeks
Completion Date: 24th October 2018
Liquidated Damages Applied: Nil

Contractor Resources

Muhammed Khan (Project Manager)
Jason Lennard (Project Engineer)
Patrick Murphy (Project Supervisor)

Principal Subcontractors

Stacpoole Drilling (Piling)
Water Industry Solutions (Sewer connection Works)
Scherzic Ground Investigations (Geotechnical Engineer)

Principal Suppliers

Hudson Civil Products (Precast Concrete)
Netco Pumps (Pumps)